Key Points;
19) Be that as it may, the loss suffered by the appellant on account of force majeure events, by itself, cannot entitle the appellant to the relief of extension of contract. Otherwise also, the appellant has not been able to demonstrate any specific clause in the contract which provides for extension of the contract on account of force majeure events. The loss, if any, suffered by the appellant on account of force majeure events or on account of delayed handing over of the parking site, can be quantified in monetary terms and it cannot be said that the appellant would suffer irreparable loss in the event the interim relief sought by the appellant is denied. Where a harm is capable of complete monetary compensation, the essential element of 'irreparable injury' is not satisfied.
Full Judgment;
IN THE HIGH COURT OF JAMMU & KASHMIR AND
LADAKH AT JAMMU
(THROUGH VIRTUAL MODE)
Reserved on: 01.09.2026
Pronounced on: 08.09.2026
Uploaded on: 08.09.2026
RFA No.50/2026
|
M/S PRATHAM TRADERS |
... APPELLANT(S) |
|
Through: - Vs. |
Mr. Pranav Kohli, Sr. Advocate, with Mr. Farhan Mirza, Advocate. |
|
UNION OF INDIA & ORS. | |
Through: - |
Mr. Vishal Sharma, DSGI, with Mr. Eishan Dadichi, CGC. |
CORAM:
HON’BLE MR. JUSTICE RAJNESH OSWAL, JUDGE
HON’BLE MR. JUSTICE M. A. CHOWDHARY, JUDGE
JUDGMENT
(I) That, admittedly, the site was not handed over to the appellant for 213 days solely on account of failure attributable to the respondents and the respondents, in their written statement, have admitted the said fact and have further admitted that the contract period was of three years but despite that, the learned Trial Court has dismissed the application for grant of interim relief, to which the appellant was entitled to in view of the categoric admissions made by the respondents.
(II) That the learned Trial Court has failed to give effect to the admission made by the respondents, as recorded in paragraph 4 of the impugned order, that the appellant's claim for “force majeure relief” is under consideration before the competent authority, therefore, publication of a fresh e-auction notice for the very same site during the pendency of the appellant's claim before the competent authority is prejudicial to the appellant's case pending consideration before the competent authority.
(III) That having expressly held in paragraphs 15, 17 and 18 of the impugned order that the contractis not determinable and is specifically enforceable, the learned Commercial Court has fallen in a palpable error of law in denying interim protection to preserve the very subject matter of the enforceable right.
appellant's rights stood extinguished byacquiescence is perverse and contrary to the record, as the appellant, on the third working day after taking possession, addressed letter dated 3rd April 2024, thereby formally recording the pendency of the earlier suit and the delay in handing over the site to the appellant. According to the appellant, silence during the continuance of a subsisting commercial relationship cannot amount to waiver of a valuable commercial right.
(V) That, in the ordinary course of the proceedings, once the impact of 213 days' deprivation began to be felt upon annualreturns and the subsequent events of force majeure intervened, then only the cause for extension arose.
(VI) That the finding of the learned Commercial Court that no irreparable injury would be caused to the appellant because theappellant is free to participate in the fresh tender, is unsustainable both in law and on facts.
(VII) That the observation made in paragraph 20 of the impugned order that force majeure events would entitle the appellant only to compensationand not to extension proceeds on a misreading of the Special Conditions of Contract. According to the appellant, the Board's letter dated 24.02.2026 directs the caseto-case consideration, having regard to the actual force majeure events and the period of loss of earnings. The measure of relief is, therefore, expressly correlated to the period of loss of earnings and extension of the contract by the period of loss is a natural and permissible consequence of such consideration.
“36. An order on an application for temporary injunction is a discretionary one, and an appellate court does not ordinarily substitute its own discretion for that of the court of first instance, save where the discretionhas been exercised arbitrarily, capriciously or perversely, or in ignorance of the settled principles governing the grant or refusal of such relief. The principle laid down in Wander Ltd. & Anr. (supra) which has been approved by subsequent decisions of this Court, has been guiding the appellate courts in the country for decades while exercising the appellate jurisdiction considering the correctness of the discretion and jurisdiction for grant or refusal of interlocutory injunctions. The order of the learned Single Judge, resting as it does on seven specific findings addressing the nature of the original plaintiff’s interest under the Will, the doubt surrounding its finality, the plea of undue influence, and the alter-ego character of the defendant entities, cannot be said to be arbitrary, capricious or perverse, nor to have been passed in ignorance of settled principle. It is, on the contrary, an order squarely anchored in the three conditions that govern the grant of interim injunction. The Division Bench’s substitution of its own appreciation of the Will, of the parties’ conduct, and of the applicability of statutory provisions bearing on the final merits, for the exercise of discretion by the learned Single Judge, was not warranted on the standard it had itself correctly recited, and constitutes precisely the kind of interference that Wander Ltd. & Anr. (supra) forbids.”
a. Declare that the Plaintiff is entitled to an extension of the contract period of Contract Agreement No. LC-23-4859014080JAT-CV dated 21.07.2023 by 213 days, on account of the delay in handingover possession of the parking site occasioned by third-party litigation and consequent inaction, and the contract shall be deemed to remain valid and subsisting up to and including 31.03.2027 (or such other date as this Hon'ble Court may determine);
b. Declare that the Plaintiff is entitled to relief under the Force Majeure clause of the Standard Conditions of Contract for the period during which its business was adversely affected on account of the floods and Operation Sindoro/Sindoor-related disruptions from on or about 26.08.2025 onward, and direct the Defendants to compute and grant such relief/extension in accordance with the Railway Board's letter dated 24.02.2026;
c. Declare that the Plaintiff is entitled to seek, and direct the Defendants to consider and grant, extension of the contract period from 3 (three) yearsto 5 (five) years in terms of Para 3(a) &3(b) of the Railway Board's letter No. 2022/TG-IV/18/Misc/E-Auction dated 28.06.2022, subject to payment by the Plaintiff of the applicable escalated license fee and additional EMD/Security Deposit;
d. Set aside E Auction issued under Catalogue No. EA-JAT-PKG-2607 (Lot No. PARKINGJAT-JAT-PCCV-24-26-1) scheduled for 17.08.2026 and PermanentProhibitory Injunction restraining the Defendants their officers, servants and agents, from finalising, confirming, acting upon or giving effect to the said E-Auction, or any other fresh auction/allotment in respect of the Commercial/Comprehensive Vehicle Parking Contract at Railway Station Jammu Tawi, or from handing over, allotting or creating any third-party right, title or interest e. Pass such other and further order(s) as this Hon'ble Court may deem just, fit and proper in the facts and circumstances of the case, in the interest of justice.
5. Therefore, the burden is on the plaintiff by evidence aliunde by affidavit or otherwise that there is "a prima facie case" in his favour which needs adjudication at the trial. The existence of the prima facie right and infraction of the enjoyment of his property or the right isa condition for the grant of temporary injunction. Prima facie case is not to be confused with prima facie title which has to be established, on evidence at the trial. Only prima facie case is a substantial question raised, bona fide, which needs investigation and a decision on merits. Satisfaction that there is a prima facie case by itself is not sufficient to grant injunction. The Court further has to satisfy that noninterference by the Court would result in "irreparable injury" to the party seeking relief and that there is no other remedy available to the party except one to grant injunction and he needs protection from the consequences of apprehended injury or dispossession. Irreparable injury, however, does not mean that there must be no physical possibility of repairing the injury, but means only that the injury must be a material one, namely one that cannot be adequately compensated by way of damages. The third condition also is that "the balance of convenience" must be in favour of granting injunction. The Court while granting or refusing to grant injunction should exercise sound judicial discretion to find the amount of substantial mischief or injury which is likely to be caused to the parties, if the injunction is refused and compare it with that it is likely to be caused to the other side if the injunction is granted. If on weighing competing possibilities or probabilities of likelihood of injury and if the Court considers that pending the suit, the subject-matter should be maintained in status quo, an injunction would be issued. Thus the Court has to exercise its sound judicial discretion in granting or refusing the relief of ad interim injunction pending the suit.”